"September 5, 2010 – The Deltec shell is up!

The foundation was erected in 5½ hours on August 23, and the slab was poured and finished on August 27. The Deltec shell was delivered on August 30, and it was erected over the following 5 days.

Monday, August 30, 2010 – Unloading the trucks

 

Tuesday, August 31, 2010 – Basement partitions and floor trusses


Wednesday, September 1, 2010 – Decking the floor


Thursday, September 2, 2010 – Erecting the shell walls


Friday, September 3, 2010 – Setting the roof trusses


Saturday, September 4, 2010 – Sheathing the roof


Sunday, September 5, 2010 – Done! The roof is self-supporting